Question: A project manager is currently facilitating the estimating process to calculate the duration of the project's activities. When she gets to the run cable activity,

A project manager is currently facilitating the estimating process to calculate the duration of the project's activities. When she gets to the "run cable" activity, one team member tells her that in a past similar project, they ran a similar length of cable in 13 hours; another team member tells her that they can run 110 meters of cable per hour. The team will need to run a total of 1320 meters of cable. Using the parametric estimating technique, how many hours will it take the team to run the cable?

a.

10

b.

13

c.

9

d.

12