Question: A project manager is determining the type and quantity of the resources needed for the project. Which process are they working in? Group of answer

A project manager is determining the type and quantity of the resources needed for the project. Which process are they working in? Group of answer choices Estimate Activity Resources Develop Schedule Expert advice from functional managers Plan Resource Management