Question: A project manager is implementing a phase of an IT project in a location that is prone to security issues. A team member, working at
A project manager is implementing a phase of an IT project in a location that is prone to security issues. A team member, working at a remote site, notifies the project manager that a permit fee was not received by the local regulatory agency involved; however, the project manager is certain that the fee was paid. The team member reminds the project manager that a test on the critical path is scheduled for that location on the same day.
What should the project manager do?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts