Question: A project manager is interested to know the approximate cost of her project so that she can identify the rationality of the vendors' offered price.
A project manager is interested to know the approximate cost of her project so that she can identify the rationality of the vendors' offered price. The best tool to use in this scenario is: Screening system Independent Estimate Inspections and Audits Weighting system