Question: A project manager is leading a high - risk project that has recently suffered from fluctuating performance and a high defect rate. During a meeting,
A project manager is leading a highrisk project that has recently suffered from fluctuating performance and a high defect rate. During a meeting, the sponsor asks for an overview of work performance and where the project is currently standing. Which of the following documents should the project manager send to the sponsor?
a Quality report.
b Status report.
c Risk report.
d Project management plan.