Question: A project manager is leading a high - risk project that has recently suffered from fluctuating performance and a high defect rate. During a meeting,

A project manager is leading a high-risk project that has recently suffered from fluctuating performance and a high defect rate. During a meeting, the sponsor asks for an overview of work performance and where the project is currently standing. Which of the following documents should the project manager send to the sponsor?
a. Quality report.
b. Status report.
c. Risk report.
d. Project management plan.