Question: A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The
A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in months.
The certification process will require at least months.
What should the project manager do next?
Discuss extending the mass production timeline by months with the project sponsor.
Meet with senior management to discuss the possibility of an extension to the project timeline.
Assess and evaluate the certification process and understand the best and worst case scenarios.
Engage a consultant to shorten the certification process to meet the schedule requirement.