Question: A project manager is managing a project in the execution phase, which was agreed upon with the sponsor However, the sponsor is constantly micromanaging and
A project manager is managing a project in the execution phase, which was agreed upon with the sponsor However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed a simplify the project How should the project manager handle the situation? Approach the sponsor about using an agite approach. Discuss reducing interruptions with the sponsor. Perform stakeholder requirements activities Review validation and control procedures