Question: A project manager is managing an industrial project using a hybrid approach. The project team has estimated that a work package will most likely require
A project manager is managing an industrial project using a hybrid approach. The project team has estimated that a work package will most likely require days to complete. If everything goes well, it could take only days. However, in the worstcase scenario, it might take up to days to complete. So the team has decided to opt for the PERT method to set a final estimate. What is the expected duration of the work package using the PERT method?
days
days
days
days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
