Question: A project manager is managing an industrial project using a hybrid approach. The project team has estimated that a work package will most likely require

A project manager is managing an industrial project using a hybrid approach. The project team has estimated that a work package will most likely require 5 days to complete. If everything goes well, it could take only 3 days. However, in the worst-case scenario, it might take up to 13 days to complete. So, the team has decided to opt for the PERT method to set a final estimate. What is the expected duration of the work package using the PERT method?
6 days
5 days
8 days
7 days