Question: A project manager is not usually responsible for making sure of which of the following? Seleccione una: a. All necessary activities are finished in proper
A project manager is not usually responsible for making sure of which of the following?
Seleccione una:
a. All necessary activities are finished in proper sequence and on time
b. The project comes in within budget
c. The people assigned to the project receive the motivation, direction, and information needed to do their jobs
d. All payments for suppliers are made correctly and on time
A restaurant decides to implement a change in its policy. During lunch hour, all meals are guaranteed to be served in 10 minutes or less, or it's free. This is an example of which type of strategy?
Seleccione una:
a. Variety
b. Response
c. Cost leadership
d. Differentiation
Which of the following is not generally considered an advantage of outsourcing
Seleccione una:
a. Greater control over quality
b. Maintaining a focus on core competencies
c. Access to outside technology
d. Cost savings
An activity in a network has the following characteristics: ES = 5, EF = 9 and LF = 12. LS = _____.
Seleccione una:
a. 8
b. 5
c. 12
d. 9
As time progresses in the last 50 years, the percentage of the workforce that is employed in the manufacturing sector:
Seleccione una:
a. Increases
b. Fluctuates (moves up and down periodically)
c. Decreases
d. Stays the same