Question: A project manager is planning a project to develop a new web site. The sponsor has requested this site be completed within a month. The

A project manager is planning a project to develop a new web site. The sponsor has requested this site be completed within a month. The scope and requirements have been elicited and documented and the project team predicts it will take two months to complete. What should the project manager do? Group of answer choices Meet with the sponsor to discuss the scope vs. time constraints Tell the sponsor the expected completion date in an email message. Tell the team to try to work faster to complete the project early. Tell the team not to worry about the due date, projects are often late