Question: A project manager is planning for project cost contingency reserves. The reserves are calculated as $ 1 0 0 0 for material costs, $ 2

A project manager is planning for project cost contingency reserves. The reserves are calculated as $1000 for material costs, $2000 for labor costs, and $3000 for equipment costs. How much money in total he is likely to put aside to deal with the combined risk of materials labor and equipment?
Question 32 options:
Less than $6000
$6000
More than $6000