Question: A project manager is preparing plans for a project that has many features / deliverables similar to a previous project. Each feature in the current

A project manager is preparing plans for a project that has many features/deliverables similar to a previous project. Each feature in the current project represents the same cost percentage as the feature in the previous project. What top-down estimating method is the project manager using?
Question 21 options:
a.apportion
b.ratio method
c.consensus
d.functionpoint