Question: A project manager is reviewing an update to a document that details the features of a planned solution. Additional features have been included for the
A project manager is reviewing an update to a document that details the features of a planned solution. Additional features have been included for the marketing department. This is an example of
a. A quality change
b. A resource change
c. A requirement change
d. A risk event