Question: A project manager is tasked with addressing the product owner's concerns about the delivery of the minimum viable product ( MVP ) in sprint four.
A project manager is tasked with addressing the product owner's concerns about the delivery of the minimum viable product MVP in sprint four. Which of the following metrics should the project manager use?
AScheduled Performance Index SPI
BSchedule Cost Index SCI
CBurndown Rate
DQualitative Risk Analysis