Question: A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used? a ) Beta
A project manager is using weighted average duration estimates to perform schedule network analysis. Which type of mathematical analysis is being used?
a Beta distribution
b Resource levelling
C Critical path method
d Monte Carlo