Question: A project manager is utilizing a probability and impact matrix during the Perform Qualitative Risk Analysis process. What would be the most likely reason for

A project manager is utilizing a probability and impact matrix during the Perform Qualitative Risk Analysis process. What would be the most likely reason for doing this? Question 6 options: To determine how risks are impacted by uncertainty To estimate the likelihood that uncertainty will influence risk management To determine the effect of risks on project objectives (if the risks occur) All of the above