Question: A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed,
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed, one of the risks
materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk
was closed.
At what point did the project manager move the risk from the risk register to the issue log
Risk managed
Risk identified
Risk monitored
Risk occurred