Question: A project manager is working with a customer who repeatedly submits new feature requests for an existing software product. The project manager has already provided
A project manager is working with a customer who repeatedly submits new feature requests for an existing software product. The project manager has already provided the completed scope definition for the product's next version release to stakeholders.
Which step is appropriate for the project manager to take next? Select one.
A. Define project boundaries immediately with the sponsor.
B. Organize a meeting with the stakeholders to set expectation.
C. Analyze the scope management plan and iterate it through the scope definition process.
D. Hold a meeting with the product manager to request that the number of new requests be reduced.