Question: A project manager is working with three key stakeholders. Each stakeholder has a different vision regarding the project and its goal. They each feel strongly
A project manager is working with three key stakeholders. Each stakeholder has a different vision regarding the project and its goal. They each feel strongly about their opinion. The project manager needs to obtain approval of the project charter.
What should the project manager do Select one.
Question options:
Use negotiation to ensure the three stakeholders are in agreement.
Conduct a stakeholder analysis.
Use the project kickoff meeting to settle the project goals.
Request that the project sponsor resolve the conflict.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock