Question: A project manager made 3-point estimates on a critical path and found the following results (in DAYS). Answer the questions: Activity Optimistic Most likely Pessimistic
A project manager made 3-point estimates on a critical path and found the following results (in DAYS). Answer the questions:
| Activity | Optimistic | Most likely | Pessimistic | PERT weighted average |
| A | 12 | 15 | 24 |
|
| B | 8 | 9 | 14 |
|
| C | 15 | 19 | 27 |
|
| D | 10 | 14 | 28 |
|
| E | 17 | 20 | 35 |
|
| Project (Total) |
|
|
|
|
All the dependencies are sequential except for the dependency between B & A which for B is defined as (Aff+2 d). When will the project finish using PERT durations?
What is the PROJECT duration estimate range?