Question: A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch
A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB). What should the project manager do now? Notify the project team about the change request's approval. Communicate the decision to the stakeholder who requested the change Include the new branch of the bridge in the design Evaluate the adjustments to the project management plan