Question: A project manager must compute the production rate for a vibratory compactor. Due to weather and the experience level of the crew, the PM expects

A project manager must compute the production rate for a vibratory compactor.
Due to weather and the experience level of the crew, the PM expects a poor efficiency
factor (approx 43minshr of productive work).
The compactor has the following specifications:
Width of the drum =71 inches
Speed while compacting =6mph
Lift thickness =8 inches
4 passes are required to meet the compaction criteria of 95% of the Modified
Proctor density.
Compute the production rate for the compactor.
Express your answer in ccyhr, to a whole number
A project manager must compute the production

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!