Question: A project manager needs to estimate the completion time for a project using the Program Evaluation and Review Technique ( PERT ) . The project

A project manager needs to estimate the completion time for a project using the Program Evaluation and Review Technique (PERT). The project has the following activities with optimistic (O), most likely (M), and pessimistic (P) time estimates: Activity A (2,4,6), Activity B (3,5,8), Activity C (1,3,5), and Activity D (4,6,9). Calculate the expected time and variance for each activity, and then determine the total project completion time and variance. Provide a detailed explanation using Excel. [ SOLVE THE QUESTION USING EXCEL]