Question: A project manager needs to estimate the completion time for a project using the Program Evaluation and Review Technique ( PERT ) . The project
A project manager needs to estimate the completion time for a project using the Program Evaluation and Review Technique PERT The project has the following activities with optimistic O most likely M and pessimistic P time estimates: Activity A Activity B Activity C and Activity D Calculate the expected time and variance for each activity, and then determine the total project completion time and variance. Provide a detailed explanation using Excel. SOLVE THE QUESTION USING EXCEL
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
