Question: A project manager planning various modules for a large-scale software development project has completed a trend analysis of previous projects. The project manager discovers that

A project manager planning various modules for a large-scale software development project has completed a trend analysis of previous projects. The project manager discovers that every project for the last two years has underestimated work and costs by at least 32 percent. The project manager decides to add a 35 percent allowance for work and budget Of what type of risk acceptance is this an example? Risk mitigation Management reserve Contingency reserve Risk reduction