Question: A project manager (PM) held discussions with a subject matter expert (SME) about the durations for a particular task. The SME said the task was
A project manager (PM) held discussions with a subject matter expert (SME) about the durations for a particular task. The SME said the task was usually completed in about 32 working days. The PM then asked the SME about the fastest and slowest times the SME could recall for the task. The SME said the worst time for a similar task was 45 days, and the fastest time for a similar task was only 22 days. What is the expected time in days using the beta distribution technique? 32.5 days 27.5 days 33 days
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
