Question: A project manager realizes more people are needed to complete a deliverable on time and asks the PMO for more resources. This is an example
A project manager realizes more people are needed to complete a deliverable on time and asks the PMO for more resources. This is an example of
| A. Shared resources |
| B. a resource shortage |
| C. interproject resource contention |
| D. benched resources |
A project manager is reviewing a project's status after it passed through its first major milestone in execution. The nine-month project is on budget, but it is already three month company's poor performance Considering these constraints, which of the following actions should the project manager suggest??
A. proceed as directed
B. Reduce the scope
C. Bring in additional resources
D. Reduce the quality metrics