Question: A project manager used information from past projects to come up with an estimate for a new software system The last few times there was

A project manager used information from past projects to come up with an estimate for a new software system The last few times there was a new release , it took about 180 days to develop . However this time , they must add in some extra features , which could add upwards of 60 days On the other hand , they may be able to secure a bigger budget , enabling overtime work for the programmers . This may cut development time by 1/3