Question: A project manager uses a causal loop diagram to determine the root cause of a serious quality problem that occurred during manufacturing. This step forms
A project manager uses a causal loop diagram to determine the root cause of a serious quality problem that occurred during manufacturing. This step forms part of the which aspect of the quality management process:
| Failure mode and effect analysis
| ||
| Quality assurance
| ||
| Quality control
| ||
| Quality planning |