Question: A project manager works in an organization that embraces using difforont projoct approaches. Tho projoct manager's current project uses a predictive approach with clear requirements.
A project manager works in an organization that embraces using difforont projoct approaches. Tho projoct manager's current project uses a predictive approach with clear requirements. A few months following the kickoff, the project manager notices that the virtual development teams are not communicating enough, and coordination is becoming an issue. The teams are not aligned on the tasks being done or the current impediments. What should the project manager do? Ask the members to be more proactive and share ideas with each other. Review the issue with the project sponsor and ask for support. Plan a monthly virtual meeting to align and review the plans. Set up a daily virtual meeting with the development team
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts