Question: A project manager works with various stakeholders including negative stakeholders mainly to overcome the resistance and gain the trust of those stakeholders. Which of the

A project manager works with various stakeholders including negative stakeholders mainly to overcome the resistance and gain the trust of those stakeholders. Which of the following skills did he use?

Writing

Negotiating

Interpersonal

Management