Question: A project manager writes a risk management plan. Currently, they are working on a description of each risk, its risk rating, and a mitigation plan.
A project manager writes a risk management plan. Currently, they are working on a description of each risk, its risk rating, and a mitigation plan. What is the name of this section in the risk management plan? Status: [object Object] 1 point Appendix Header Risk register Executive summary