Question: A project needs preventative actions to meet security requirements and to avoid corrective actions if audited. One of the stakeholders does not agree with the

A project needs preventative actions to meet security requirements and to avoid corrective actions if audited. One of the stakeholders does not agree with the success criteria. How should the project manager capture the performance in the closure report?

  • A. Align the report to the acceptance criteria and the definition of done (DoD).
  • B. Follow the actions necessary to satisfy the exit criteria.
  • C. Use the schedule performance index (SPI) and cost performance index (CPI) to measure success
  • D. Refer to the project risks and issue register that was maintained throughout the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!