Question: A project network and related data are shown below. The manager would like to reduce the project duration to 15 weeks in the least expensive
A project network and related data are shown below. The manager would like to reduce the project duration to 15 weeks in the least expensive way.
a) Formulate a linear programming model for this problem.
b) Obtain an optimal solution using Excel Solver. You must submit an Excel file with Solver set up and optimal solution shown.