Question: A project network has the following paths. How much slack does path ABEHJL have? Path ABDGIK Duration 23 Path ABEHJL Duration 24 Path ACFIKL Duration

A project network has the following paths. How much slack does path ABEHJL have?
Path ABDGIK Duration 23
Path ABEHJL Duration 24
Path ACFIKL Duration 31
A. 7
B. 24
C. 0
D. 8