Question: A project network is shown in the figure. 3 For the project represented above, determine the earliest and latest start and finish times for

A project network is shown in the figure. 3 \\ For the project represented above, determine the earliest and latest start and finish times for each activity. Activity | Duration ES LS EF LF Slack A 7 | | B 5 ] ] c 7 ] ] D 3 ] ] E 8 ] ] F ; ] ] G 8 | | H 10 ] ] Determine the expected overall completion time