Question: A Project plan is required to be prepared for the work tendered below, using Microsoft Project 2000 Software, or later, or any other suitable project

A Project plan is required to be prepared for the work tendered below, using Microsoft Project 2000 Software, or later, or any other suitable project software. Notes should accompany the project assignment describing the details and thinking behind the project form. The project should show such features as:

Gantt chart with tasks, dates, bar charts, etc. showing linked tasks with any lead or lag times critical path resources list completed resources usage task usage 7 tracking Gantt chart resource fixed and task costs project % completion and cost report(s) tasks that can start simultaneously or prior to the finish of their predecessor, if any.

Task usage with associated costs (resource and task costs) should be simulated for the project at 100 % completion and reports produced. Hard copies of the project assignment are required. CDs or floppy disks can also be submitted. It should be noted that the critical path view must be saved as a separate project or as a screen dump figure pasted into, say, Paint, which is usually available in Microsoft Office (or Word) Programs/Accessories on the Start Menu. This is because, if resources are assigned to tasks the critical path is obscured and shows in normal task colour. Any views that may be lost in the course of completing the project must be saved at an appropriate time. Alternatively students may wish to do a power point presentation of various views of their project.

It is worth using the first task as a repository for making notes about the project as one progresses. This is done by selecting Project/Task Notes which brings up a dialogue box into which can be typed notes and memos, such as foreman is not assigned to task (a) because this task is performed on the same day as task (b) to which the foreman has already been assigned, etc. Leaving the resources dialogue box open and assigning resources will leave the same resources selected for repetitive tasks, which facilitates resource assignment. Alternatively, if there are many repetitive tasks, by holding down the Control key each repetitive task can be highlighted and then by selecting the Assign Resources icon (or Tools/Assign Resources) and entering the resources data in the dialogue box all the tasks selected will be updated without having to select each task individually. This same technique can be applied to task progress tracking, by holding down the Control key each repetitive task can be highlighted and then by selecting Tools/Tracking/Update Task, and entering the progress data (e.g. 100 %, actual duration and remaining duration) all the tasks will be updated without having to select each task individually.

Tender plan

Work activity amount rate cost
Materials
Lanterns 20 10 200
Ballast 20 5 100
Ignitor 20 5 100
Capacitor 20 5 100
Column 20*6*4metre 10.per metre 4800
Cable 20*10 metre 10 2000
Photo electric cell 20*1 50 1000
Tarmac 20*10kg 10 2000
Concrete 20*15kg 10 3000
Hiring charges
Crane 10 days 200 per day 2000
Hiab 10 days 300 per day 3000
Concrete mixer 5 days 100 per day 500

Total material and hiring cost - 18800

Work plan amount rate cost
Excavation of holes 20+ 20 hrs 10 per hour 400
Hiab operator 10 days 200 2000
Wiring of new lamps 20 hours 10 per hour 200
Column installation 20 hours 10 per hour 200
Lantern attachment 20 hours 5.per hour 200
Temporary reinstatement 10 days 100 per day 1000
Permanent reinstatement 5.days 100 per day 500
Transport charges 2000
Contigency 2000
Wastage allowance 2000
Depot security 1000
Admin and management 4000
Contract manager 2000
Drawings cost 1000

Total labour and fixed cost - 18500

Total cost - 37300

Profit margin - 10% - 3730

Total tender cost - 41030

Assumptions used -

Firstly all old and new holes are excavated - 40 holes.

It takes one hour to excavate one hole - 40 manhours

5 people with 8 hour shift are deployed for hole excavation in one day.

Everyday two new lamps are completed and old lamp removed

So it takes 10 days of hiab work

Two lamps of one street are kept working and two are removed every day. So lighting disruption is minimal.

Lamps are purchased and paid for by client

Temporary reinstatement happens every day - 10 days

Permanent reinstatement happens after work of a street is completed - every alternative day - 5 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!