Question: A project proposal was made to construct a warehouse building for a sum of 75,000.00 USD. Total construction period forecasted was Three (03) moths commencing

A project proposal was made to construct a warehouse building for a sum of 75,000.00 USD. Total construction period forecasted was Three (03) moths commencing from 10th July 2021. Project manager has planned to complete 40% of the project at the end of 1st month. But the completed value of work done after one month is 27% only. Actual cost at the end of first month is 27,500.00 USD. Treat 10th August 2021 as the status day

A. Work out the following

(i) Earned Value ( EV)

(ii) Planned Value( PV)

(iii) Cost Performance Index (CPI)

(iv) Schedule Performance Index (SPI)

(v) Cost variance ( CV)

(vi) Schedule variance(SV) Show all above in diagram drawn with cost against time.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!