Question: A project requires 6 9 2 , 5 0 0 CY , bank measure, of rock - earth mixture, which will be excavated by a

A project requires 692,500 CY, bank measure, of rock-earth mixture, which will be excavated by a 2-CY front shovel. The material will be loaded into 15-CY, loose measure truck, and hauled 4 miles to the project. The trucks will average 25 mile/hour loaded and 30 mile/hour empty. Assume 5 minutes to dump a truck load.
The front shovel can excavate the rock-earth mixture at the optimum depth of cut and at a 120 average angle of swing. It will cost $2,400 to transport the shovel to the Job, set it up to operate, and return it to the storage yard.
Assuming the rock-soil mixture has a swell factor of 45%. Use TABLE 7.11,7.12, and 7.13 as needed.
Estimate the total cost and the cost per cubic yard, bank measure, for excavating and hauling the earth. Assume that the shovel and trucks will operate at a 45-minute per hour efficiency. Determine the economical number of trucks to balance the production rate of the backhoe with the hauling rate of the trucks. The following cost
information applies:
Front Shovel $105.00/hour
Trucks, each $34.85/hour
Shovel operator $23.50/hour
Truck drivers, each $19,75/hour
Foreman $29.80/hour
TABLE 7.11 I Fill factors for front shovel buckets.
Source: Caterpillar, Inc.
TABLE 7.12| Time for elements in a shovel
production cycle.
Note: These values are for shovels with 3- to 5-cy buckets. TABLE 7.13 I Conversion factors for depth of cut and angle of swing for a power
shovel.
Source: Power Crane and Shovel Association.
A project requires 6 9 2 , 5 0 0 CY , bank

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!