Question: A project requires specialized technical expertise from the engineering department. However, the senior engineer is leading a team on a separate project, and the only

A project requires specialized technical expertise from the engineering department. However, the senior engineer is leading a team on a separate project, and the only available resource is an entry level engineer. The senior engineer is highly regarded by the customer and preferred by the project manager. What should the project manager do first to obtain the senior engineers participation in this project?