Question: A project returns 15% when the market returns 10% and 8% when the market returns 15%. Calculate the projects market beta Question 29 options: +0.7
A project returns 15% when the market returns 10% and 8% when the market returns 15%.
Calculate the projects market beta
Question 29 options:
|
| +0.7 |
|
| -0.7 |
|
| -1.4 |
|
| 0.0 |