Question: A project schedule that doesn't adhere to any schedule specifications or to the schedule specifications dictated by the contract and scheduling best practices and guidelines
A project schedule that doesn't adhere to any schedule specifications or to the schedule specifications dictated by the contract and scheduling best practices and guidelines in general will:
Group of answer choices
A-Be a grave error on the general contractor's part for non-compliance of the contract.
B-More than likely not be an approved project schedule by the owner.
C-Place the general contractor at low risk for using a schedule with scope of work that is not clear.
A and B