Question: A project segment consists of three tasks. Task A is scheduled to begin at the start of week one and finish at the end of
A project segment consists of three tasks. Task A is scheduled to begin at the start of week one and finish at the end of week three. Task B is scheduled to begin at the start of week one and finish at the end of week two. Task C is scheduled to begin at the start of week two and end at the end of week three. Budgeted cost for Task A is $ for Task B is $ and for Task C is $
Your initial budget included a total contingency of $ Balance of your contingency fund remains strong with $ of $ remaining after week one. However, unforeseen construction conditions require using $ of this contingency balance in week two. percent of unused contingency is returned to project owner. This project has a very high level of risk, supporting a risk factor of which equates to labor coverage of $ Coincidentally, labor costs are running approximately over budget due to project complexity.
At the end of week two, Task A is complete, Task B is complete, and Task C is complete. Actual cost of work for tasks A B and C performed at the end of week two for project segment in Problem is $ and none of your allocated risk factor funds have been used.
Calculate estimated cost to complete for project segment based on information in this problem and project schedule performance index for tasks A B and C corresponding to end of week two. Assume cost performance index remains stable throughout remainder of project and labor budget stabilizes.
A project segment consists of three tasks. Task A is scheduled to begin at the start of week one and finish at the end of week three. Task B is scheduled to begin at the start of week one and finish at the end of week two. Task C is scheduled to begin at the start of week two and end at the end of week three. Budgeted cost for Task A is $ for Task B is $ and for Task C is $
Your initial budget included a total contingency of $ Balance of your contingency fund remains strong with $ of $ remaining after week one. However, unforeseen construction conditions require using $ of this contingency balance in week two. percent of unused contingency is returned to project owner. This project has a very high level of risk, supporting a risk factor of which equates to labor coverage of $ Coincidentally, labor costs are running approximately over budget due to project complexity.
At the end of week two, Task A is complete, Task B is complete, and Task C is complete. Actual cost of work for tasks A B and C performed at the end of week two for project segment in Problem is $ and none of your allocated risk factor funds have been used.
Calculate estimated cost to complete for project segment based on information in this problem and project schedule performance index for tasks A B and C corresponding to end of week two. Assume cost performance index remains stable throughout remainder of project and labor budget stabilizes.
$
$
$
$
$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
