Question: A project task has been determined to be beta distributed in terms of cost. At best, the task will cost $3,000. At most the task
A project task has been determined to be beta distributed in terms of cost. At best, the task will cost $3,000. At most the task will cost $5,000. Mostly likely the task will cost $3,500. What is the standard deviation of the cost of this task?