Question: A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The
A project team has completed the first iteration and the testing manager approved the test report, indicating that the acceptance criteria have been met. The manager of the business unit that will use the new product is asking for additional functionality before approving the rollout for their team. What should the project manager do next? Reschedule the rollout to include the new requirements. Escalate this issue to the project management office (PMO). Escalate this issue to the project sponsor. Reschedule the rollout to start with another business unit
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
