Question: A project team has made up the work breakdown structure for a project. Senior management for the company and all of the stakeholders including the

A project team has made up the work breakdown structure for a project. Senior management for the company and all of the stakeholders including the client have approved the WBS. The client later requests that a change be made in the project, which will cost a considerable amount of money. The client says that the companys salesman promised this feature prior to sign-off on the WBS. Who should pay for the change