Question: A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because
A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because there are questions from team members from opposite time zones. What should the project lead do? Escalate to the project sponsor and request to replace certain team members so the time zones are aligned. Meet each team member during their work hours to ensure all questions are answered in a timely manner. Inform all team members that they are required to check for messages every few hours to ensure fast response times During daily check-ins, compile questions, coordinate with all team members, and agree to meet