Question: A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.What should the project manager doA Set up a meeting with key stakeholders to clarify requirementsB. Escalate to the project steering committee and request additional timeC. Travel to the development team's office to push the scheduleD. Create prototypes with the development team to confirm requirements