Question: A project team is performing a post - release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have
A project team is performing a postrelease evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.What should the project manager do in this situation?Host a meeting with the reluctant stakeholder and project team to resolve any conflict.Schedule a meeting with the reluctant project stakeholder to obtain their feedback.Explain to the sponsor why the reluctant stakeholder needs to provide feedback.Meet with all seven of the project stakeholders and request all of their feedback.