Question: A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase
A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some reserves needed What should the project manager do to successfully complete the next phase? Request a reserve analysis and update the risk management plan. Review the risk response plan to verify inclusion of the needed reserve. Perform a schedule network analysis to avoid any critical path delays. Update the risk response plan to include the needed reserve