Question: A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some reserves needed What should the project manager do to successfully complete the next phase? Request a reserve analysis and update the risk management plan. Review the risk response plan to verify inclusion of the needed reserve. Perform a schedule network analysis to avoid any critical path delays. Update the risk response plan to include the needed reserve

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock