Question: A project team is starting the construction phase for a very large reverse osmosis water treatment plant. This project has numerous contractors, and the local
A project team is starting the construction phase for a very large reverse osmosis water treatment plant. This project has numerous contractors, and the local government, the community, and vanous institutions have different expectations. In the past, similar projects have had a significant number of claims. What should the construction professional do to address this risk? Create a website for the project and provide continuous visibility of progress. Invite community and local government representatives to risk workshops Ensure alignment on the project's purpose, scope, and contract documents Establish the appropriate controls for decision-making within the project